How Did SMSCL Help?
Client: Perenco
SMSCL was contracted by Perenco to upgrade their piping flow piping system.
Southern Maintenance was entrusted with the complex task for the fabricating and installing the piping upgrading system.
SMSCL successfully completed the project scope below:
OBJECTIVE
- Fabricate, Weld, NDE and final painting of the Deck Reinforcement Beams & Plates as Identified in Drawings (See Drawing in Appendix D)
- Shop Works-: Contractor is required to pre-fabricate, Blast and Prime and deliver to Galeota Warehouse in certified CCUs Main Beams, Pipe, and Deck plates.
- Field Works-: Contractor is required to field install Prefabricated Beams, Deck Plates and Piping -: Fabricate, Weld, NDE and Final Painting/Touch up of the Deck Area as Identified in DWG.